Successful installation on a challenging roof saves 350 kg of CO₂ per day

Quick installation on the roof of a large commercial building

The installation took place on the roof of a commercial building with a total area of 8900 m2. The goal was to find the optimal solution for significant electricity savings in the building.

Icon/20x20/Arrow-left Created with Sketch. Bobrky, Vsetín, Czech Republic

Setting the scene

The planning and actual implementation of this large project took a total of 3 months. The installation took place on several roofs of a production and warehouse hall for the automotive industry under very strict requirements of the investor.

 

Meeting the challenges

The project was challenging for the installation company due to the low static load capacity of the roof and the obstacles on the roof. These challenges were effectively solved with the Solar-Planit configurator.

 

Result

Taking into account the low load capacity of the roof and the customer's requirement for a quick implementation, this project was very successful. The installation covers the main consumption of the building, motivating a further 1.5 MWp of capacity. This project saves 350 kg of COper day.